Leave Your Message

China Suppliers Factory EP10405 Thick-Film Epoxy Anti-Corrosion Paint for Ship Bottoms - Iron Red

This high-performance marine two-component epoxy iron red primer is manufactured by leading China suppliers. Formulated with iron oxide red, this primer effectively stabilizes on steel surfaces through chemical passivation. By incorporating flake fillers, it creates a robust physical barrier that effectively blocks water vapor and oxygen, ensuring superior corrosion protection. Ideal for metal structures above water surfaces that are not submerged for extended periods, this product is a reliable choice from a trusted factory committed to quality and durability

    Product Characteristics
    🌊
    Good corrosion resistance to seawater environments.
    🛡️
    Excellent shielding properties against chloride ions.
    Recommendations
    ✅
    Used for surface corrosion protection of metal and cement at sea and underwater.
    Product Parameters
    Project Data
    Density (Kg/L) 1.45
    Color Iron Red
    Solid percentage by volume % 72 ± 2
    Reference dry film thickness (μm) 125
    Theoretical coating rate (㎡/L) 5.8
    Flash point 30°C [86°F]
    Volatile matter (g/L) 225
    Gloss Matte
    Drying time 10℃ 20℃ 30℃
    Dry to touch 180 mins 120 mins 90 mins
    Actual drying 24 hrs 10 hrs 8 hrs
    Coating interval 10℃ 20℃ 30℃
    Min 8 hrs 6 hrs 4 hrs
    Max 15 Days 8 Days 5 Days
    Potlife 10℃ 20℃ 30℃
    6 hrs 4.5 hrs 4 hrs
    Mixing ratio Base : Hardener (4:1 by volume)
    Storage period 24 months @ 25°C
    Application
    Construction Method
    🔧
    Method: Airless spraying
    🔧
    Nozzle pressure: 14 MPa – 21 MPa
    🔧
    Nozzle hole diameter: 0.6 mm – 0.8 mm
    ℹ️
    If applying by brush or roller, additional coats will be required to achieve the specified dry film thickness. Spray data is for reference only and may be adjusted. Pressure is applicable to material temperatures of 20°C [68°F]. Brush and roller application is only suitable for line marking and small area touch-ups.
    Construction Conditions
    🌡️
    During construction and curing, the surface temperature of the substrate must be above 5°C [41°F].
    💧
    To avoid condensation, the substrate temperature during construction should be at least 3°C [5°F] higher than the dew point, clean and dry.
    🌬️
    Relative humidity: The relative humidity during construction and curing must be less than 85%.
    Surface Treatment
    ✔️
    Remove oil, grease and other contaminants with a suitable cleaning agent.
    ✔️
    High-pressure water cleaning removes salt, detergents and other contaminants.
    ✔️
    Surface blasted to Sa 2½ (ISO 8501-1) / SP 10 (SSPC).
    ✔️
    Remove dust, sand and loose materials.
    ✔️
    Surface blasted to PSa 2½ (ISO 8501-2) / SP 10 (SSPC).
    ✔️
    High pressure water is sprayed onto Wa 2½ (ISO 8501-4).
    ✔️
    Small areas can be cleaned by hand or electric tools instead of sandblasting.
    ✔️
    The degree of flash rust is not higher than FR L (ISO 8501-4).
    ✔️
    The surface of the substrate reaches Medium (G) (ISO 8503-2).
    Disclaimer
    ⚠️ The information provided in this manual is the most comprehensive and correct information we have at present. Since the conditions of product use are beyond our control, the information here does not contain any guarantee, that is, we are only responsible to the buyer for the product selection. Due to the continuous development of our company's products and production processes, all information here is subject to our confirmation.
    Frequently Asked Questions (FAQ)
    Q
    What surfaces is this paint suitable for?
    This paint is designed for surface corrosion protection of metal and cement structures used at sea and underwater, providing strong resistance to seawater and chloride ion penetration.
    Q
    What is the recommended application method?
    Airless spraying is the recommended method, with a nozzle pressure of 14–21 MPa and a nozzle hole diameter of 0.6–0.8 mm. Brush or roller application is acceptable for small touch-up areas, but additional coats will be required to achieve the specified dry film thickness.
    Q
    What are the required surface preparation standards before application?
    The surface should be blasted to Sa 2½ (ISO 8501-1) / SP 10 (SSPC). All oil, grease, salt, dust, and loose materials must be removed. For previously coated surfaces, PSa 2½ (ISO 8501-2) / SP 10 (SSPC) applies. Flash rust must not exceed FR L (ISO 8501-4).
    Q
    What environmental conditions are required during application?
    The substrate surface temperature must be above 5°C [41°F] and at least 3°C [5°F] above the dew point to avoid condensation. Relative humidity must remain below 85% throughout construction and curing.
    Q
    What is the mixing ratio and pot life of this product?
    The mixing ratio is Base : Hardener = 4:1 by volume. The pot life varies by temperature: approximately 6 hours at 10°C, 4.5 hours at 20°C, and 4 hours at 30°C. Always prepare only the quantity that can be used within the pot life.
    Q
    How long is the storage period and what are the storage conditions?
    The product has a storage period of 24 months when stored at 25°C. Ensure the product is kept in a cool, dry environment away from direct sunlight and extreme temperatures to maintain its performance properties.

    Leave Your Message